• Minister Luke Pollard told Parliament the Ministry of Defence is assessing how inflation, labour and supply chain pressure affect Type 31 frigate costs and affordability.
  • He declined to give the approved budget limit or a completion date for the review, citing commercial interests, and did not say whether more money would be needed.
  • In May, Babcock disclosed a £140 million cost adjustment on the programme for rework and productivity problems; five ships are being built at Rosyth.